Challenge

A precast concrete factory needed cranes to handle floor slabs, columns, beams, and wall panels weighing up to 20 tons. The cranes had to cover a large production area and lift long pieces with balance.

Solution

D2 Cranes installed double girder cranes with twin hoists for balanced lifting of long pieces. Extended runway beams covered the entire production area with multiple cranes on the same runway.

Scope of Work

  • 4 double girder cranes (10 and 20 ton capacity)
  • Twin hoist system for balanced lifting
  • 200-meter runway covering entire production area
  • Inter-crane anti-collision system
  • Radio remote with twin hoist control
  • Load testing and operator training

Result

The 4-crane system on the same runway operated smoothly without collisions. Precast concrete production capacity increased by 30% through faster piece handling.